Modernization of 7 Production Lines for a New Model Launch – Without Stopping Production

Client
BMW, a global manufacturer of premium vehicles, initiated a project to launch a new vehicle model at its Munich plant. Introducing the new model required adapting existing production lines to the latest technological and industry standards.
Challenge
The modernization scope covered 7 main production lines operating in continuous mode. A key project requirement was to complete all work without interrupting ongoing production.
Modernizing active production lines in the automotive environment involves high operational risk. Any unplanned downtime can generate significant costs and impact production schedules.
Unlike building a new production line, modernizing existing infrastructure requires taking into account the dependencies between equipment already in operation, PLC controllers, and other automation systems. Changes to the control logic of one station can affect other parts of the production process, so every modification requires careful analysis and validation. Another challenge is the need to align the project schedule with ongoing production. All changes must be carefully planned to ensure that the production lines can resume normal operation in accordance with the plant’s requirements once testing is complete.
BMW required the following:
- reprogramming of existing control systems,
- integration of the lines with the latest industry and corporate standards,
- preparation of the infrastructure for production of a new vehicle model,
- modernization of 7 main production lines,
- ensuring full operational continuity of the plant,
- preparation of documentation and user training.
The project required precise planning, phased implementation of changes, and close cooperation with the plant’s operational teams.

Solution
The team applied a phased and controlled approach to modernizing the control systems.
- Phased Implementation of Changes
The modernization was divided into planned stages executed during defined operational windows, which enabled:
– gradual updates of PLC program,
– testing of changes in a controlled environment,
– elimination of risks to ongoing production.
Dividing the modernization project into stages allowed us to align the scope of work with the availability of individual production lines. Preparing the PLC software modifications in advance and defining the sequence of implementation and testing were essential. This approach enabled us to introduce changes in a controlled manner without having to shut down the entire production infrastructure at once. Each stage required verifying that the modified systems operated correctly before returning them to production. - Validation of PLC Control Logic Changes
Modernizing PLC software requires verifying that the changes work correctly with the existing equipment configuration and do not negatively affect other functions of the production line. Validation includes checking control sequences, signal exchange between devices, and system responses to specific operating conditions. Particular attention must be paid to testing the interactions between modified stations and the remaining infrastructure. This helps identify potential issues before returning the production lines to operation and reduces the risk of problems caused by changes to the control software. - Integration with the Latest Standards
We updated the control systems to ensure compliance with current industry standards as well as BMW’s corporate guidelines regarding software architecture, safety, and documentation. - Documentation and Knowledge Transfer
We prepared comprehensive technical documentation covering changes in control systems and production line structure. Additionally, we conducted training sessions for operators and technical personnel, ensuring a smooth handover of the modernized systems to the client’s team. Up-to-date control system documentation is particularly important when modernizing existing production lines. It helps maintenance and automation teams understand the changes made, diagnose potential issues more quickly, and safely plan future modifications. Documenting changes to PLC logic and equipment configuration also reduces the plant’s dependence on the knowledge of individual specialists, making it easier to maintain and operate the modernized infrastructure.

Results
The project was completed with full implementation of changes and without any disruption to ongoing production at the Munich plant.
Achieved outcomes:
- modernization of 7 main production lines,
- Launch of a new vehicle model without production downtime,
- Integration of systems with the latest industry standards,
- Preservation of full operational continuity at the plant,
- Comprehensive technical documentation supporting ongoing maintenance,
- Trained personnel prepared to operate the new system.


AI Automates Geotechnical Documentation Analysis and Speeds Up Proposal Preparation
Design, Development, DevOps or Cloud – which team do you need to speed up work on your projects? Chat with your consultation partners to see if we are a good match.
Jakub Orczyk
Member of the Management Board/ Sales Director VM.PL
Book a free consultation

AI/ML